constraining tasks and connecting them
I'm new to OmniPlan (and Macs) and I'm trying to figure out how to connect 2 tasks for which the first task needs to happen 15 weeks before the second task (the second task has other relationships which determine its timing). I tried playing with connections with lead times, but that wasn't doing it for me...
Any help would be great! |
Dependency connections with lead times sounds like the right way to do it, so could you provide more details about how it "wasn't doing it" for you?
|