hngtme 2007-08-12 06:16 PM

Leveling Hour By Hour
 
Hello,

You would be my hero if you can tell me how to level hour by hour and have Omniplan break up tasks when necessary to achieve the quickest schedule. I am trying to account for meeting activities in my plan by including them as tasks and not modifying the allotted work time. Is this possible? Please tell me yes as I want to use this app for my project I am starting. I have found tracking in Omni plan to be easier and better then in Project.

Also, any chance of a Pert entry form for tasks?

Help!
Greg

skwirl 2007-08-22 10:28 AM

[QUOTE=hngtme;19176]Hello,

You would be my hero if you can tell me how to level hour by hour and have Omniplan break up tasks when necessary to achieve the quickest schedule. I am trying to account for meeting activities in my plan by including them as tasks and not modifying the allotted work time. Is this possible? Please tell me yes as I want to use this app for my project I am starting. I have found tracking in Omni plan to be easier and better then in Project.

Also, any chance of a Pert entry form for tasks?

Help!
Greg[/QUOTE]

Hi Greg,

OmniPlan isn't able to level hour by hour and break up the tasks accordingly at this time. We have some feature requests for the ability to split a task into multiple parts, which could in turn be used during leveling. I'll add a vote to this for you.

As for a PERT entry form, this is at the top of our features to add list.