-   -   More problems working with MS Project (http://forums.omnigroup.com/showthread.php?t=11051)

sabeke 2009-01-13 12:57 PM

More problems working with MS Project
 
MS Project uses [I]Work[/I] and [I]Duration[/I]. OmniPlan uses [I]Effort[/I] and [I]Duration[/I]. When creating a schedule in MSP, you set the [I]Duration[/I] and the [I]Work[/I] field stays at 0 until you assign resources. If the schedule is imported into OP, it appears that MSP's [I]Duration[/I] field is copied over to both OP's [I]Duration[/I] and [I]Effort[/I] fields. Upon export to xml, the [I]Effort[/I] field is copied to the MSP's [I]Work[/I] field. MSP thinks that resources are assigned and this causes problems.

I purchased OP based solely on its advertised ability to work with MS Project. I have spent over a week trying to figure out how to successfully use OmniPlan with MS Project on a real project and have gotten nowhere.

Have you guys actually tried using OmniPlan with MS Project?

whpalmer4 2009-01-13 01:09 PM

[QUOTE=sabeke;53643]
Have you guys actually tried using OmniPlan with MS Project?[/QUOTE]
Nope, I haven't. I hope to keep it this way, too :-)

Seriously, you should be sure to also send email to [email]omniplan@omnigroup.com[/email] (or use Help->Feedback) to make sure the Omni folk are seeing your questions. What with the recent holidays and then Macworld, I suspect everyone is digging out from under a ton of backed up work, and reading the forums isn't high on the priority list.

sabeke 2009-01-13 05:53 PM

[QUOTE=whpalmer4;53644]Seriously, you should be sure to also send email to [email]omniplan@omnigroup.com[/email] (or use Help->Feedback) to make sure the Omni folk are seeing your questions.[/QUOTE]

Good idea, thanks

skwirl 2009-01-19 12:20 AM

[QUOTE=sabeke;53643]MS Project uses [I]Work[/I] and [I]Duration[/I]. OmniPlan uses [I]Effort[/I] and [I]Duration[/I]. When creating a schedule in MSP, you set the [I]Duration[/I] and the [I]Work[/I] field stays at 0 until you assign resources. If the schedule is imported into OP, it appears that MSP's [I]Duration[/I] field is copied over to both OP's [I]Duration[/I] and [I]Effort[/I] fields. Upon export to xml, the [I]Effort[/I] field is copied to the MSP's [I]Work[/I] field. MSP thinks that resources are assigned and this causes problems.[/QUOTE]

The reason this is happening is because OmniPlan doesn't support unlinking Duration and Effort when there are no resources assigned to a task while Microsoft Project does. When a file from Microsoft Project is imported into OmniPlan with a Duration value but no Effort value OmniPlan recalculates this and sets the Effort to be the same as Duration. We're going to work on this in our next version, but there's no workaround for this currently.