How to require multiple resources at the same time?
 
Hi,
So, I'm trying to schedule some tasks that requires two specific people to be involved at the same time. I've assigned myself and another person both as resources for these tasks, and I've customized my work schedule to remove days when I will be out of the office, but when I click "Level", it schedules the tasks for days when I am not available. Is this a bug, or is there some other way I should be assigning things?
Thanks,

Ellen

ned 2012-03-27 11:33 AM

I'm struggling with this exact thing. I have a task that requires two people to complete. I assign them, but when I level the project OP schedules this task to occur when one of them is not available (as defined by their work schedule). Is there any way to take this into account?