-   -   feature request re: default task values for effort (http://forums.omnigroup.com/showthread.php?t=5932)

ext555 2007-11-29 07:43 AM

feature request re: default task values for effort
 
I"d like to be able to specify the default setting for effort on newly added tasks .
8h doesn't fit everyone's work style .

skwirl 2007-12-17 11:03 AM

[QUOTE=ext555;26849]I"d like to be able to specify the default setting for effort on newly added tasks .
8h doesn't fit everyone's work style .[/QUOTE]

The default effort setting is based off what your conversion factors are set to in the "Project : Formatting" inspector. Simply change it from 8 hours to whatever setting you want and that should do it.