etvaxed 2012-01-31 02:55 AM

Total cost on task bars in GANT view
 
Hi, preparing a GANT layout of a project for a customer. It would be nice to have costs at the right end of each task bar in the GANT scheme, how?

DSpearman 2012-02-21 06:27 AM

Go to the View menu and select the menu item 'View Options'. Edit the task labels so that "Total Task Cost" is in view to the left or right of the appropriate Gnatt item.