locking the start of a task immediately upon completion of the previous task
This is probably one of my first threads here, I'm very happy with the overall usability of OmniPlan, I'm taking notes on suggestions/improvements very often along the way.
One of the features I'm looking for is locking the start of a subsequent task immediately upon completion of the previous task, so even leveling can't mess it up by making gaps between them. My workaround behind this, is assigning a very high priority to both tasks, but a more convenient way is to be able to check a box somewhere in the inspector, like a "locked or solid F->S", any plans on implementing this feature ? Thanks |