vil 2007-10-31 05:05 AM

Updating assigned units
 
Hi everyone,

So, I've set the unit %s for each of my staff and assigned tasks to them; I've then gone and changed the unit %s for the staff, but each task still records the original % value. What I have now is a lot of tasks where Fred Bloggs is assigned at "50% of 70%" instead of "70% of 70%".

Is there an easy way to update all of these to the maximum % value for the staff member?

skwirl 2007-11-06 09:55 PM

[QUOTE=vil;23785]Hi everyone,

So, I've set the unit %s for each of my staff and assigned tasks to them; I've then gone and changed the unit %s for the staff, but each task still records the original % value. What I have now is a lot of tasks where Fred Bloggs is assigned at "50% of 70%" instead of "70% of 70%".

Is there an easy way to update all of these to the maximum % value for the staff member?[/QUOTE]

You can select all the tasks that need to be changed by holding the CMD key while clicking on each task. Once they're highlighted, bring up the "Task : Information" inspector and you'll be able to type in "70% of 70%" to apply it to all your highlighted tasks.