Problem interacting with MS Project
 
Hi all,

I'm using OmniPlan 1.6.1 in conjunction with a large group of people at work who are using MS Project. We are on a large program with multiple subsystems. As part of our program management/cost accounting process, we track %complete for each task and that is used to bill the customer.

Each subsystem lead is responsible for creating and maintaining their own schedule. The schedules are to be updated and turned in weekly. Program management then uses these to generate progress reports and billing.

I am having a problem with OmniPlan that is causing a hiccup in the system. In MS Project, there is [I]Start[/I] and [I]Actual Start[/I]. The default is for planning to use [I]Start[/I] and [I]Actual Start[/I] is blank (or N/A). When a task is started then the [I]Actual Start[/I] is filled in.

In OmniPlan, there is [I]Planned Start[/I] and [I]Start[/I]. It appears that setting the baseline just copies the dates in [I]Start[/I] to [I]Planned Start[/I] but they remain in [I]Start[/I]. After exporting my plan and opening it under MS Project, MS Project now thinks I have started all of my tasks. This is causing problems with our system.

Has anyone else encountered this problem? If so, how did you work around it (short of going into MS Project and editing all the Actual Start dates by hand)?