jianqiang82 2014-05-16 03:27 PM

How do you make group's tasks running simultaneously
 
Group 1 ...3d
Task 1 ...1d
Task 2 ...1d
Task 3 ...1d

Using the example above, how can I make the group task show 1d instead of the entire groups 3days combined?

For example, these 3 tasks can all be completed in one day. Therefore I want the group's effort to also be 1d.

So instead of saying each task takes 2.66h, is there a way to leave them at 1d and the group not adding up all the tasks together?

I've fiddled with assigning resources, fixing effort and duration, and can't figure it out.

Thanks!