How to see only task groups that have started? [A: See thread.]
Is there a way that I can see only tasks or groups that have started - so, if I wanted to start working on something next monday, but it wasn't due until next Friday - could I have a perspective setting that would list tasks that have started? Thanks - First time on the forum.
|
If you only want to see items which have started, including those with no start date, bring up a context mode view showing Available options. If you also want to eliminate items which do not have an explicit start date, do the same, except group by start date, and close the groups containing the actions you don't want to see. Save the view as a perspective for easy use in the future.
This post should go in one of the OmniFocus forums... |
Thanks - trying to figure out how to get there and post.
|