7.5hr day still results in 8hr default tasks
Hi All,
I'm hoping there's an easy solution to this: My organisation uses a 7.5 hour working day, so I've changed both the Normal Working Week and the Project: Unit Conversions data from the default 8 hour working day to use 7.5 hours. However when I enter a task, its default duration is 1 day 0.5 hours, e.g. it is still using the default 8 hour working day settings. Can this be adjusted? Any tips appreciated! Cheers, Alex |
Create a task that is in all ways how you want your newly created tasks to be*— background color, duration, effort, etc. Select Project->Set as Default for New Tasks and all tasks you subsequently create for the project will use that as a template. (Note however that if you change your "template" the existing tasks will not update, OmniPlan just takes a snapshot of what your task looked like at the time you issued the command).
|
Ah! Simple :)
Thanks for the tip, much appreciated. Cheers, Alex |
All times are GMT -8. The time now is 06:20 AM. |
Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.