abusch 2006-08-02 02:01 AM

Bug: Problem with changing work schedule
 
Trying to change the work schedule for a person (inserting two days of non-availability in a specific week), I run into problems and cannot alter the schedule. (By the way -- how is one supposed to do this? I do it with the mouse, dragging the end of the week to shorten it and then add another day).

The error message is "[NSCFArray insertObject:atIndex:]: index (2) beyond bounds (1)"

Nat 2006-08-02 10:16 AM

1 Attachment(s)
I have the same problem... Moreover the central calendar differ from the one on the bottom left.
nat

Brian 2006-08-02 10:37 AM

[QUOTE=abusch]The error message is "[NSCFArray insertObject:atIndex:]: index (2) beyond bounds (1)"[/QUOTE]

I got this to happen once, but then failed to reproduce it when I subsequently tried to do so. If anyone manages to put together a reproducible case of this, please send it to us via Send Feedback. Thanks!