I"d like to be able to specify the default setting for effort on newly added tasks .
8h doesn't fit everyone's work style . |
[QUOTE=ext555;26849]I"d like to be able to specify the default setting for effort on newly added tasks .
8h doesn't fit everyone's work style .[/QUOTE] The default effort setting is based off what your conversion factors are set to in the "Project : Formatting" inspector. Simply change it from 8 hours to whatever setting you want and that should do it. |