the3rdParty 2013-07-23 10:28 PM

Working weekends for only some tasks
 
I am trying to plan a project that has a team in the office which works & bills a 5 day week, and a team in the field which works and bills a 7 day week. Office and field tasks occur simultaneously.

I am aware that I can set the working week for the whole project via Calendar view, but what I want to do is set the working week for particular tasks.


Is this possible?


Many thanks

jim