Charlotte 2012-07-13 09:07 AM

T Day
 
I am currently creating a critical path template for multiple projects which should follow the same deadline. So what I did is set the date as undetermined. But I would like to set each task to a specific timeline, so when I put in the actual date for baseline the whole schedule can automatically populate the right dates to each task. Is there a way to do that? I tried to simply type in the date formula as T-XXd or T-XXw, it doesn't seem to work. For example, when I typed T-36w in start date or end date, it gives me T-42w 4d. What did I do wrong???

Please help...Thank you!