What are those gray bars?
1 Attachment(s)
What are those gray bars before the task duration blue bars on the Gantt?
[ATTACH]2949[/ATTACH] |
I figured it
|
You have start no earlier than constraints on those tasks. Since the constraint may be off screen to the left, we kind of draw a slot that OmniPlan is free to slide the task along as it satisfies other scheduling requirements.
|