The Omni Group Forums

The Omni Group Forums (http://forums.omnigroup.com/index.php)
-   OmniPlan General (http://forums.omnigroup.com/forumdisplay.php?f=37)
-   -   What are those gray bars? (http://forums.omnigroup.com/showthread.php?t=31051)

xamxmith 2013-11-16 11:37 AM

What are those gray bars?
 
1 Attachment(s)
What are those gray bars before the task duration blue bars on the Gantt?

[ATTACH]2949[/ATTACH]

xamxmith 2013-11-17 02:49 PM

I figured it

Tom Bunch 2013-11-18 02:15 PM

You have start no earlier than constraints on those tasks. Since the constraint may be off screen to the left, we kind of draw a slot that OmniPlan is free to slide the task along as it satisfies other scheduling requirements.