-   -   2 dependencies in the same task (http://forums.omnigroup.com/showthread.php?t=7953)

Kimsake 2008-05-12 05:04 AM

2 dependencies in the same task
 
How can I create FF and SS between same pair of tasks. When I add FF then SS will gone. Vice Versa.

Kimsake 2008-05-12 05:19 AM

To make it clearer, I need Ladder dependency type

Lizard 2008-05-16 12:08 PM

This isn't directly possible. One work-around would be to create an intermediate milestone. So as an example, for the start dependency you'd go A->C->B, and for the end dependency you could go straight from A->B.