Adding Tasks/Milestones
 
I often insert one or more tasks in a project. Inserting works fine, however if I hit return and get a new task, and decide I do not need another line and hit command Z, not only is the new line removed, but the text in the previous line that I typed in is removed and substituted with "Task 1" as if I had just added that. I think it should just remove the line your are on, not the previous work.

Lizard 2006-09-29 09:40 AM

We've had a few reports of that. I've added your notes.