The Omni Group Forums

The Omni Group Forums (http://forums.omnigroup.com/index.php)
-   OmniFocus 1 for Mac (http://forums.omnigroup.com/forumdisplay.php?f=38)
-   -   Show action group in context mode? (http://forums.omnigroup.com/showthread.php?t=15454)

ryantate 2010-02-28 11:40 AM

Show action group in context mode?
 
Hello all, I'm wondering if it's possible to show action groups in context mode, alongside the tasks they contain. My tasks don't make much sense when divorced from the action group, so even though I have the Project showing in context mode, this isn't enough information.

For example, here's a slice of my context view:

[IMG]http://ryantate.com/screenshots/OmniFocusScreenSnapz005.jpg[/IMG]

This is confusing: What am I emailing Brian about? What ideas am I asking Sylvia about? The only way to find out is to switch to project mode so I can see the action groups. From the project "Chapter 1:"

[IMG]http://ryantate.com/screenshots/OmniFocusScreenSnapz001.jpg[/IMG]

From project "Chapter 2:"

[IMG]http://ryantate.com/screenshots/OmniFocusScreenSnapz003.jpg[/IMG]
[IMG]http://ryantate.com/screenshots/OmniFocusScreenSnapz004.jpg[/IMG]

With the action groups in view, the tasks suddenly make sense. But you really shouldn't have to switch out of context mode to see this info. Ideally, within context mode, the task "Email Brian L" would be followed by "Find Mystery Developer / Interview Mystery Developer / Chapter 1 - PlayStation" instead of just "Chapter 1 - PlayStation".

If it's not possible to enable this -- can someone tell me whether it is or not? -- I'll certainly be emailing this in as a feature request to OmniGroup. In the meantime, as a workaround, I could go through all the tasks (that I just dumped in for this new set of projects) to manually rewrite them with the contextual info as such - "Email Brian L to find mystery developer for interview".

But my wrists already hurt thinking about all that typing :->

ryantate 2010-02-28 02:12 PM

Prior threads
 
OK it looks like this has been asked about in years past, including in the thread "[URL="http://forums.omnigroup.com/showthread.php?t=12637"]Feature Request: Subprojects/Action Groups in Projects breadcrumb[/URL]" and "[URL="http://forums.omnigroup.com/showthread.php?t=10636"]action groups don't appear in context views[/URL]." (I tried searching before I posted, but not with Google.)

There is an "official" solution to this -- Ken [URL="http://forums.omnigroup.com/showpost.php?p=18378&postcount=37"]mulled[/URL] in 2007 that perhaps action groups should "show up in context view when their children are complete" and sure enough in[URL="http://forums.omnigroup.com/showthread.php?t=15345&highlight=action+group"] the 1.8 nightlies there's this feature[/URL]:
[INDENT]Groups, Projects, and Inbox items now show up in Context lists, Due lists, and Flagged lists. When actions are sorted by project, parent items follow their children (which is the natural order for completing them). Single Action Lists are not actionable, and do not appear in Context lists.[/INDENT]

This is really not a solution at all if you're using Action Groups as subgroups;
[LIST][*]my task names would still make no sense since we don't get action group breadcrumbs in Context view AND [*]the name of the Action Group in my case ("Find gaming expert") is not always a task unto itself. [*]And even if I made all Action Group names into tasks (not sure this would work), there's not yet a way to assign context to the Action Group so it doesn't show up in a Perspective unless you have "No Context" selected.[/LIST]
Another thing Ken suggested was to turn Action Group into Projects. This then implies the parent Project should be a folder. Two problems:
[LIST][*]Project tasks that weren't in action groups now need to become their own single-action projects which is silly and[*]If you drag an action into a folder, OmniFocus helpfully converts it into a Project and STRIPS all context information from it. Oy.[*]Folders do not have the ability to specify sequential vs parallel the way Projects and Actions Groups do so you lose information.[/LIST]
Basically what needs to happen is that Action Groups need to become full fledged nested Projects. In Context view, Sub project names would be displayed with full breadcrumb trail showing all parent projects to the right of one another. OmniGroup could then nuke the whole concept of Folders and use parent Projects in their place (why not?). Then you'd end up with ONE type of object where you once had THREE. Which makes the software easier to learn.

ryantate 2010-02-28 02:23 PM

Feedback
 
------

BevvyB 2010-03-02 08:07 AM

I actually quite like making up new projects which I know come directly after other projects (ie one can't be started until the other is completed)

Currently I put them on hold and activate them once the other project is done. What would be much better is some kind of start-date-dependency

i.e. Start video project when the music project is completed

or even

Start video project when such and such action is completed

That would give you the ability to show / hide projects based on the completion of not just other projects but other actions - which would give great flexibility ESPECIALLY as time and time again project start times overlap - sometimes the pre-production for something starts half way through another project once a specific action or milestone is met or completed.

Some nifty way of adding the start date in the start date box as a dropdown of other projects would be a good start - or something like that! Be nice not to have to use the inspector for this.

Brian 2010-03-02 03:14 PM

I'm pretty sure we have a feature request open on showing action group names in context view in some fashion: emailing the [EMAIL="omnifocus@omnigroup.com"]support ninjas[/EMAIL] and let the team know you'd like to see that happen.

In the meantime, I'd recommend making action names understandable/actionable on an individual basis as much as possible. Using a random example from earlier in the thread, "Email Brian L and Jane to find mystery developer" is a similar amount of typing to the nested pair of actions, but is more understandable when viewed later in context view.

Does that help at all? You lose a bit of flexibility since you can't check the emails off individually, but overall, it seems better than the current situation. :-)


All times are GMT -8. The time now is 06:56 AM.

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.