Total Cost blank if assign task to resource group.
Hi all,
I've setup a group 'software dev team' with 4 members. I've allocated a cost/hour to each member. The cost/hour of the group is the average cost of each member. So far so good. But if I assign the group to tasks with associated 'effort' values the 'total cost' column remains blank. if i associate the tast to an individual resource i get a correct calculation. What am i doing wrong? |
I ran into the same problem and filed a bug report for it a few weeks ago. Apparently this is not yet solved in the 1.1 beta.
|
Thanks for the reports. It's in our database and we've got top men working on it.
-Tom [SIZE="1"]"Who?" "Top... men."[/SIZE] |