TimothyMDean 2008-09-16 07:38 AM

Changing resource allocation over time?
 
When setting up resources for a project, each resource's availability varies over time. For example, this month John can be allocated 50% to this project, but next month he can be allocated 75% to this project.

Is there a way to set this up in OmniPlan?

- Tim

skwirl 2008-09-18 03:52 PM

Not at the moment. We have a feature request for this in our database so I'll add a vote for you. Right now you'll need to make a new task each time the resource allocation needs to change.

pslade 2008-09-19 05:19 AM

Please add a vote for me also