1 week is 5 days? What if it's 7?
Hi,
I have a team working 7 days a week. I start a new project. It has one default task. I set it's duration to 1 w. I go to calendar view. I set the project calendar to 7 days active. I switch back to Gannt. The task now says 1 w for duration but shows as only five days on the Gannt chart. I have to set it to 1w 2d to have it show a line spanning 7 days on the Gannt chart. Any help appreciated. Thanks // :) |
Bring up the Project : Formatting inspector. Adjust the effort conversion factors to match your needs. Also see this thread: [URL="http://forums.omnigroup.com/showthread.php?t=10949"]http://forums.omnigroup.com/showthread.php?t=10949[/URL]
|
Thanks // :)
|