charlax 2012-03-02 01:22 PM

Zero effort task
 
Hey,

How would you create a task that has no effort?

For instance, I have the following tasks:

1- Prepare the request for proposal
2- Launch the request for proposal
3- Receive the answers
4- Choose the winner

Task 3- does not need any effort but will be at least one week in duration. How do I do that?

Thanks for your help!

whpalmer4 2012-03-02 01:41 PM

How about a milestone with a lead time of 1 week?

[URL=http://imageshack.us/photo/my-images/17/screenshot20120302at239.png/][IMG]http://img17.imageshack.us/img17/8440/screenshot20120302at239.png[/IMG][/URL]

charlax 2012-03-02 04:01 PM

Thanks! That's a great & efficient answer.