Task Groups
Hi all.
Is this possible to assign resource to a Parent(known as group in OmniPlan) task directly? When i try to assign resource to a group OmniPlan assigns it to each task in group, it's very strange behavior. In MS Project I can assign different resources to parent and to children tasks, it is very useful, especially when you have parallel children tasks. OmniPlan is just amazing, but I can't use it without this feature. Any Idea? Thank you and excuse me my written english, I'm not native |
This isn't possible right now. We have a feature request for this in our database so I've added a vote for you.
Curious, what do you expect to happen when a resource is assigned to a group task? We think assign a resource to a group task means you want to assign the resource to all tasks within the group. |