danielgjohnston 2007-08-07 08:23 AM

Cumulative Days in Gantt Chart
 
Is it possible to display cumulative days along the X axis in the Gantt chart? I need to plan a project using cumulative days, rather than calendar days.

Lizard 2007-08-13 09:38 AM

Not sure it's exactly what you're after, but this might help.
1) Open the Project: Information inspector
2) Change the Start: to "Undetermined Date"
This will change the headings to things like "Day 17" and "Week 3"

danielgjohnston 2007-08-21 01:37 PM

Great suggestion
 
Your suggestion will work. I had hoped to get cumulative days, but cumulative weeks works for my project. Thanks!

Lizard 2007-08-21 02:29 PM

You can have cumulative days by zooming in more. Click the magnifying glass in the upper right corner of the Gantt chart and choose Days.