fire00 2009-10-06 10:53 AM

Wrong date assignment? [A: Action assigned to project/group with earlier due date.]
 
ladies and gentlement & folks!

have you seen the following behviour on your omnifocus?

When a "due date" is assigned for a task, then after "clean-up" and in the "Due-View", the task is assigned in a wrong due category.

Example:
1. Create task with due date "next week"
2. Clean up
3. Go to "Due View"
4. The same task is shown under "Due within the last week"

Mac OS X 10.6.1
Omnifocus 1.7.4
Macbook Pro 13"

Lucas 2009-10-06 12:56 PM

You may want to check whether the action's project or an action group containing that action has a due date within the last week.

fire00 2009-10-06 03:25 PM

lucas thanks, that was the trick :)