Task turned Hammock; its effort reduced (SOLVED)
1 Attachment(s)
I'm trying to create a hammock task. In attempting to recreate the tutorial (glue; let glue dry; spray top coat), I've set a "let glue dry" effort of 3H. After creating the dependencies the way I *think* they're supposed to be, and then turning the "let glue dry" task into a hammock, it's duration is reduced to .25H (or whatever effort I set the "spray top coat" task to. In the attached .png, I have no resource attached to the hammock task, but even when I assigned it to a resource "factory", the results are the same. Perhaps my dependencies are wrong.
The attached PNG is how things look just prior to to changing the task 2 to a hammock task. |
Omni explained to me that I just need to set the start date/time of task 3 to wherever is needed, to adjust the length of the hammock. Problem solved.
|