skeskali 2010-03-22 01:58 PM

Effort Conversion Factors
 
I work in an office were the average work day is 7.75 hours, but when I enter this into the Project:Formatting pane in the inspector, it rounds my time up to 7.8 hours. Is there anyway to force OmniPlan to use the number I've entered?

Thanks!

Tom Bunch 2010-03-24 09:39 AM

Wow, I'm kind of surprised I haven't seen reports of that. In our infinite wisdom at some point we decided nobody would want precision into the 1/100 of an hour, but I'd sure rather think in terms 1/4 hours than .1 hours.

Please send feedback and we'll log a bug. Obviously, the solution is to change to using metric time.

Kidding.

-Tom