msbendle 2007-10-09 03:35 AM

Date sub header
 
Hello-

I need the ability to insert the month in the coulmns created within the "quarter" timescale.....it looks like you should be able to do this already but I can't seem to get it...

Either way I am trying to make reading the gnatt chart more user friendly when viewing large projects...

Thanks
Matt

skwirl 2007-10-09 04:10 PM

[QUOTE=msbendle;22480]Hello-

I need the ability to insert the month in the coulmns created within the "quarter" timescale.....it looks like you should be able to do this already but I can't seem to get it...

Either way I am trying to make reading the gnatt chart more user friendly when viewing large projects...

Thanks
Matt[/QUOTE]

You actually can't do this in OmniPlan 1.1.2, but this is something we're working on in the next update to OmniPlan.