The Omni Group Forums

The Omni Group Forums (http://forums.omnigroup.com/index.php)
-   OmniPlan General (http://forums.omnigroup.com/forumdisplay.php?f=37)
-   -   Mixed tasks for same resource (http://forums.omnigroup.com/showthread.php?t=7374)

Archemedia 2008-03-04 04:59 AM

Mixed tasks for same resource
 
I'd like to have some advice on how to achieve the following:

In a simple project, there are 2 tasks, each taking 3 days of work.
There is only 1 resource, which is assigned to the 2 tasks.

After assigning, the resource is overallocated (200%) so I have to level the project.

The result is that the first task in my list will be handled before the second task giving my resource 6 days of work. The first 3 days on task #1 and the following 3 days on task #2

My question:
[B]How can I obtain that my resource will work on BOTH tasks for 50% during 6 days?[/B]

skwirl 2008-03-13 12:41 AM

[QUOTE=Archemedia;33823]I'd like to have some advice on how to achieve the following:

In a simple project, there are 2 tasks, each taking 3 days of work.
There is only 1 resource, which is assigned to the 2 tasks.

After assigning, the resource is overallocated (200%) so I have to level the project.

The result is that the first task in my list will be handled before the second task giving my resource 6 days of work. The first 3 days on task #1 and the following 3 days on task #2

My question:
[B]How can I obtain that my resource will work on BOTH tasks for 50% during 6 days?[/B][/QUOTE]

You can select the task, bring up the "Task : Assignment" inspector, and change the percentage to 50% of 100%. Do this for the other task and you'll be smooth sailing. :-)

cwingrav 2009-03-06 07:56 AM

[QUOTE=akwong;34400]You can select the task, bring up the "Task : Assignment" inspector, and change the percentage to 50% of 100%. Do this for the other task and you'll be smooth sailing. :-)[/QUOTE]

Great, now, is there some support for more complicated operations? I have the same issues but I want to say, "Both occur over this period and end at the same time." i.e. simultaneously. But, one task takes 25w and another takes 4w. Sure, I can manually calculate the percent but is there an automated way?

i.e. 25/29 ~= 86% and 4/29 ~= 14%

Or, is there a way to say, "50% of your time on X and the rest on the remaining projects?"


All times are GMT -8. The time now is 07:14 AM.

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.