dannyw 2011-12-13 04:02 AM

Move entire project to new end date
 
Hi,
I set up a project 6 months ago that has now finished. I now need to re-schedule exactly the same project to finish at a new end date.

I thought this would be a simple process. I've tried putting in a new end date and clicking 'backward from fixed end'.... this doesn't work. I've tried selecting and dragging the entire project to the new end date....this doesn't work either. I'm sure there's a simple way to re-schedule projects that repeat, but I can't work it out!!

Please help!

whpalmer4 2011-12-13 07:43 AM

Try this:

Duplicate the project file
Open the duplicate
Bring up the project information inspector (command-4)
Change the start date to be about today
Look at the resulting finish date in the line along the bottom of the project window and compare it to your desired finish date. Iteratively adjust the start date until you hit the target.

Now go look the resulting project over carefully, because there are things that are likely to have shifted around due to holidays, starting on different days of the week, and all the other stuff that makes one week not just like every other week.

Working backward from a fixed end is a good thought, but it works only if the original project was constructed that way, too.

dannyw 2011-12-13 12:45 PM

Thanks will try this in the morning!

The original project was constructed backwards from from the end date. It seems crazy that the ability to re-schedule / re-use a successful project timeline doesn't appear to be included in the program.

I use the same project timeline / critical path twice a year and I purchased Omniplan, thinking that I could just amend the end date and the tasks etc would move accordingly. I honestly thought that this would be a basic feature?

Thanks again for your help. Much appreciated.

dannyw 2011-12-14 06:36 AM

Nope...didn't work.
I've managed to get the project to start on todays date, but when I try and move the start date I get a new start date in the inspector and on the bottom left of the screen, but the actual Gantt chart doesn't move and neither does the end date.

Seems like Omniplan can't perfom this simple task.

Is there anyone out there who has any ideas??

whpalmer4 2011-12-14 07:57 AM

Can you send your plan? If you go to Help ->Send Feedback, it will ask you if you want to include your plan, and if a you agree, it attaches a file which has everything identifiable in your plan replaced with Task 1, Task 2, or xxxxx. Then send it to me at gmail, or use the message as it into send it to Omni support (add a note referencing this thread). I think there might be something with how you constructed your plan that is causing you grief here, as I was able to shift some plans in the fashion I described.

dannyw 2011-12-14 09:24 AM

That would be great. What's your gmail address?