Overlap with dependent tasks
When using Microsoft Project I could set one task with a duration, for example 2 weeks. I could then set another task as dependent on that one but specify that it was due to start part way through the other... [task1 FS - 1week].. (task 1's finish date minus 1 week).
How can I do this in Omni Plan? How can I specify overlapping tasks that are also dependent tasks? Thanks //:) |
I answered a similar question here: [URL="http://forums.omnigroup.com/showthread.php?t=13833"]http://forums.omnigroup.com/showthread.php?t=13833[/URL]
but I'll also do yours as an example. [URL=http://img44.imageshack.us/i/picture13zx.png/][IMG]http://img44.imageshack.us/img44/8060/picture13zx.png[/IMG][/URL] |
Awesome, that works! Thanks // :)
|