Effort not summing correctly?
Apologies for this if it's covered elsewhere, I did look but could not find it.
I'm looking to move away from MS Project and so am using Omniplan to create simple/medium project schedules for multiple projects we have going on. However, I think I've noticed something a little concerning. The effort for individual tasks does not look like it is summing correctly into the summary/group tasks. It's quite possible I'm missing something, but I opened a new schedule to recreate the issue and added some simple tasks to it and the same issue occurred. I didn't do anything special other than add some individual tasks into the group, then delete them. I have a screenshot I'll look to upload somewhere and make available. Thanks |
Here's a quick screenshot. Look at summary task 1.3 and sub tasks.
Thanks (hope I worted the image link ok...) [IMG]http://farm4.static.flickr.com/3132/2297254190_13068d4ce8_o.png[/IMG] |
All I see is a "this photo is currently unavailable".
Try sending the screenshot as an email attachment to [email]omniplan@omnigroup.com[/email] |
Hi, already addressed with Aaron at the support email.
turns out no screenshot is required. Steps to repeat bug: 1. Create new schedule with 1 summary task which contains 2 tasks. Summary Task 1 Task 2 2. Drag Task 2 so that it appears above Task 1. you'll notice that the summation of effort shown against the Summary line increases by the effort of Task 2. 3. You can repeat if you drag Task 1 above Task 2 again, etc, etc. This is purely a display issue with open schedules. If you close the schedule and reopen it, efforts are correct. Thanks |