HunterHillegas 2012-06-22 08:56 AM

Cost Estimates for Milestones or Groups
 
I see the cost estimate for the whole project. Is it possible to see the cost estimate for a grouping or milestone (i.e. just 'development' instead of the whole project)?

Thanks!

HunterHillegas 2012-06-22 09:15 AM

I guess you could expand this question - I'm a little confused about how costs and resources work.

For instance, I have a bunch of tasks in a milestone, say 'app' and that milestone is one of a few in a group, say 'development'.

The tasks have time estimates. They are attached to a resource that has an hourly cost.

I can see an overall project cost estimate but if I look at any of the specific containers (i.e. 'development' or 'app'), I can't seem to see a cost for that component.

For milestones and groups, I have the option to add extra 'Task Cost' but it's not clear what that cost is supposed to be attached to if not the resources via the tasks.

I'm guessing I'm just looking in the wrong place. I did read the manual but it doesn't seem to cover everything. Are there other documents I should read? Is the Mac manual useful for understanding some of this stuff? I've never used OmniPlan before the iPad app.