How to ensure a task is not split between days?
I am scheduling a task (a phone conference) that is expected to last two hours. Right now, based on prior tasks, it shows as starting during the last work hour of one day, and continuing over to the first work hour of the next day. The call cannot be done that way. It needs to be done in a 2-hour period, not 2 different 1-hour periods.
Any advice on how to accomplish that? |
I haven't found a built-in mechanism you could use for that without some fiddling. I would suggest laying out your plan, finding the date on which the task ends, and then applying a start and end constraint to the task to force the start and end to both be on that date.
[URL=http://imageshack.us/photo/my-images/861/screenshot20120619at425.png/][IMG]http://img861.imageshack.us/img861/5318/screenshot20120619at425.png[/IMG][/URL] |
Thanks. That will do the trick.
|
All times are GMT -8. The time now is 11:25 PM. |
Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.