Repeating tasks, only non zero delays allowed
There are some projects - like painting the Forth Bridge - that begin again as soon as they're complete.
I'm not a bridge painter but I do have a project like this. But it seems that the minimum repeat time is an hour. Is there any reason a repeat time of zero can't be allowed, obviously not for "repeat every" but certainly for "start after"? |
You can set a start again time to 1 minute, and the new task will actually be created immediately after checking the current task as complete.
|
[QUOTE=Greg Jones;97054]You can set a start again time to 1 minute, and the new task will actually be created immediately after checking the current task as complete.[/QUOTE]
Hmm, not on the iPad version (all I have with me). The smallest unit is an hour and the smallest value is 1. Did you manage to get that 1 minute by typing freeform text into the repeat time or are the selectable units smaller on the desktop and I just missed it? |
There are smaller units on OmniFocus Mac, which is the forum you posted your question in! ;)
|
[QUOTE=Greg Jones;97056]There are smaller units on OmniFocus Mac, which is the forum you posted your question in! ;)[/QUOTE]
Oops ;) I'll try it on the Mac when I get home and see what happens when I sync one of these. |
I just tried it myself and the iPad does retain the 1 minute start again time for the tasks that have the repeat set on the Mac.
|