Forum: OmniPlan General
2010-05-06, 10:13 AM
|
Replies: 2
Views: 10,472
Counting weeks
I have a task with a start date of June 7 2010 (task 3.4.1.1) (Monday).
I created a milestone with a constraint of 3.4.1.1SS+2w.
The milestone date is June 18 2010 (Friday).
I expected the...
|
Forum: OmniPlan General
2010-04-17, 02:15 PM
|
Replies: 1
Views: 7,030
Monday 8 AM is different from Friday 5 PM
Hi Everyone,
I have several tasks for which the duration is specified such at that the task ends Friday at 5 PM. But, I want to show the deliverable being due at Monday 8 AM. I don't care if...
|
Forum: OmniPlan General
2010-02-16, 12:38 PM
|
Replies: 9
Views: 11,378
|
Forum: OmniPlan General
2010-02-16, 12:22 PM
|
Replies: 5
Views: 8,462
|
Forum: OmniPlan General
2010-02-14, 01:39 PM
|
Replies: 5
Views: 8,462
|
Forum: OmniPlan General
2010-02-14, 12:21 PM
|
Replies: 5
Views: 8,462
Not getting daily increments
I have "daily scheduling" selected in the project inspector, but when I type "2w" or "5w" for the duration of some tasks, they automatically convert to a duration of "2w 2h" or "5w 7h" (for example)....
|
Forum: OmniPlan General
2010-02-09, 05:15 PM
|
Replies: 0
Views: 8,769
|
Forum: OmniPlan General
2009-10-06, 04:53 PM
|
Replies: 0
Views: 9,949
How to represent weekly meeting
(Caution! New user - please be patient if the answer is obvious - I have looked in the manual and in this forum but couldn't find a good answer)
I'm looking for recommendations for how to...
|
Forum: OmniPlan General
2009-09-23, 02:26 PM
|
Replies: 5
Views: 16,543
Export/save/print part of a schedule
I have a schedule that started 6 months ago. I want to export the schedule from a week ago through the next few months in some PDF or other format that non-Omni-plan users can view (or some other...
|
Forum: OmniPlan General
2009-09-12, 08:46 PM
|
Replies: 1
Views: 9,022
Define constraint as a function of another task?
(I'm a new user - please excuse the basic questions - I am searching the forum and reading the manual but not finding everything that I think is likely to be possible)
I have a series of tasks,...
|
Forum: OmniPlan General
2009-09-12, 05:48 PM
|
Replies: 1
Views: 12,387
Define group to be 100% complete
I have a group that includes several tasks.
Rather than setting the percentage completion of each individual task to 100%, is there a way to "declare" the group to be complete (so that all of the...
|
Forum: OmniGraffle General
2006-08-11, 08:47 AM
|
Replies: 9
Views: 19,199
|
Forum: OmniGraffle General
2006-08-10, 02:34 PM
|
Replies: 9
Views: 19,199
|
Forum: OmniGraffle General
2006-08-04, 10:17 AM
|
Replies: 9
Views: 19,199
|
Forum: OmniGraffle General
2006-08-04, 10:05 AM
|
Replies: 9
Views: 19,199
connecting lines to lines
Using Omnigraffle 3.2.4.
I'm trying to draw two lines that are perpendicular with each other - one horizontal and the other vertical. The horizontal line should terminate at the vertical line...
|