Group end and Task end issue
I am finding that sometimes if a task ends say at 9:20pm and the group that the part of the task is constrained to end at 9:20pm, the task shows up at ending after the group ends.... What is causing...
|
Forum: OmniPlan General
2010-02-18, 12:39 PM
|
Replies: 34
Views: 33,549
|
Forum: OmniPlan General
2010-02-16, 07:04 PM
|
Replies: 2
Views: 5,183
|
Forum: OmniPlan General
2010-02-16, 05:00 PM
|
Replies: 16
Views: 10,552
|
Forum: OmniPlan General
2010-02-16, 04:59 PM
|
Replies: 16
Views: 10,552
Right, but assign a resource. Then change the...
Right, but assign a resource. Then change the hours of work per day. My point is that the Duration column in the WBS should be the same as the length of the activity bar in the Gantt. My exp was...
|
Forum: OmniPlan General
2010-02-16, 04:56 PM
|
Replies: 7
Views: 10,762
I agree with you. But at the same time, there...
I agree with you. But at the same time, there are really two types of Critical Paths people want to see. First they want to seethe critical path for timeline just like it is currently. But we also...
|
Forum: OmniPlan General
2010-02-16, 04:17 PM
|
Replies: 16
Views: 10,552
|
Forum: OmniPlan General
2010-02-16, 04:16 PM
|
Replies: 16
Views: 10,552
Right so the Gantt bar should span over the 4...
Right so the Gantt bar should span over the 4 days in your first example. What i am saying is that when you change the Hours of a day in the Project settings, and have custom work days, the...
|
Forum: OmniPlan General
2010-02-16, 03:36 PM
|
Replies: 16
Views: 10,552
Ok but that does not explain by the Gantt does...
Ok but that does not explain by the Gantt does not update. The gantt shows the duration. So shouldnt the Gantt and the Duration column be equal to each other? Meaning that if i change the project...
|
Forum: OmniPlan General
2010-02-16, 02:38 PM
|
Replies: 16
Views: 10,552
|
Forum: OmniPlan General
2010-02-16, 01:55 PM
|
Replies: 16
Views: 10,552
|
Forum: OmniPlan Extras
2010-02-15, 10:09 PM
|
Replies: 6
Views: 16,019
|
Forum: OmniPlan General
2010-02-15, 10:04 PM
|
Replies: 7
Views: 10,762
|
Forum: OmniPlan General
2010-02-15, 08:44 PM
|
Replies: 7
Views: 10,762
|
Forum: OmniPlan General
2010-02-15, 08:41 PM
|
Replies: 7
Views: 10,762
Ok most likely in this case then i have a few...
Ok most likely in this case then i have a few activities which are locked in dates. These dates cannot occur as early as possible. They have to be exact dates. Will the critical path not continue...
|
Forum: OmniPlan General
2010-02-15, 08:07 PM
|
Replies: 7
Views: 10,762
Critical Path Question
I am having some issues with the Critical Path. When i run critical path, the very last 2 activities and final mile stone get marked as critical path, but nothing else connected through dependencies...
|
Forum: OmniPlan General
2010-02-15, 04:48 PM
|
Replies: 2
Views: 5,183
Auto Lead Time
Is there a way to set a default lead time? for all tasks? Or maybe a script that would add a default lead time to all tasks or selected tasks?
|
Forum: OmniPlan General
2010-02-15, 04:47 PM
|
Replies: 3
Views: 4,265
|
Forum: OmniPlan General
2010-02-15, 03:55 PM
|
Replies: 1
Views: 7,121
Bug: Priority Column WBS Auto-highlight
When you are on activity 1 in the effort column and press the down arrow key to activity 2 the effort is automatically selected/highlighted.
When you are in the Priority Column and do the same...
|
Forum: OmniPlan General
2010-02-15, 03:52 PM
|
Replies: 3
Views: 4,265
FR: Colour Coding Days
Would be great if we could be able to mark days with colours. So say Friday Feb 26 was a very important day (for whatever reason). I could mark that day/column in red. Or even mark entire activity...
|
Forum: OmniPlan General
2010-02-15, 03:49 PM
|
Replies: 1
Views: 4,566
Merge Inspector into Main Window
Is there a way to merge the inspector into the main window?
I know you can just resize the window to account for the inspector, but i find it nice sometimes to have the inspector window locked...
|
Forum: OmniPlan General
2010-02-15, 12:32 PM
|
Replies: 0
Views: 3,834
Summary Header level Gridline Colours
We need a way to change the summary level gridlines in the Gantt. So for example i am working with a gantt atm with summary level that shows: [First day of week] - [last day of week] [Month] ...
|
Forum: OmniPlan General
2010-02-15, 12:27 PM
|
Replies: 1
Views: 6,228
|
Forum: OmniPlan General
2010-02-15, 12:24 PM
|
Replies: 16
Views: 10,552
|
Forum: OmniPlan General
2010-02-15, 12:15 PM
|
Replies: 1
Views: 6,228
Printing Outline with Gridlines??!!
Is there not a way to print the WBS outline (without Gantt) with gridlines. Even better quesiton is there a way to add gridlines to the WBS within omniplan?
I know you can use the HTML report to...
|