Forum: OmniPlan General 2012-01-18, 05:23 AM
Replies: 2
Views: 5,858
Posted By metasim
Fixed Cost, Fixed Duration, Flexible Effort/Resources

I'd like to know if it's possible to create a fixed duration task, with a fixed cost, and have OmniPlan automatically tell me how many hours of a resource are available (based on an hourly rate...