Forum: OmniPlan General 2010-02-21, 11:09 AM
Replies: 0
Views: 4,610
Posted By stephenrussett
Group end and Task end issue

I am finding that sometimes if a task ends say at 9:20pm and the group that the part of the task is constrained to end at 9:20pm, the task shows up at ending after the group ends.... What is causing...
Forum: OmniPlan General 2010-02-18, 12:39 PM
Replies: 34
Views: 33,253
Posted By stephenrussett
Well said. Though OOP would not even really...

Well said.

Though OOP would not even really be needed. By OF and OP integration would be great. Or even some HTML reports for work that needs to be done for each resource
Forum: OmniPlan General 2010-02-16, 07:04 PM
Replies: 2
Views: 5,132
Posted By stephenrussett
THANKS. I am not good with apple script and i...

THANKS. I am not good with apple script and i think this will help me out big time.

Thanks you 100x over I will give it a try a few days from now :)
Forum: OmniPlan General 2010-02-16, 05:00 PM
Replies: 16
Views: 10,443
Posted By stephenrussett
I will try to create a more hardened example...

I will try to create a more hardened example later tonight for you to try.
Forum: OmniPlan General 2010-02-16, 04:59 PM
Replies: 16
Views: 10,443
Posted By stephenrussett
Right, but assign a resource. Then change the...

Right, but assign a resource. Then change the hours of work per day. My point is that the Duration column in the WBS should be the same as the length of the activity bar in the Gantt. My exp was...
Forum: OmniPlan General 2010-02-16, 04:56 PM
Replies: 7
Views: 10,658
Posted By stephenrussett
I agree with you. But at the same time, there...

I agree with you. But at the same time, there are really two types of Critical Paths people want to see. First they want to seethe critical path for timeline just like it is currently. But we also...
Forum: OmniPlan General 2010-02-16, 04:17 PM
Replies: 16
Views: 10,443
Posted By stephenrussett
You can set the normal working days to 9-830pm...

You can set the normal working days to 9-830pm sun-sat
Forum: OmniPlan General 2010-02-16, 04:16 PM
Replies: 16
Views: 10,443
Posted By stephenrussett
Right so the Gantt bar should span over the 4...

Right so the Gantt bar should span over the 4 days in your first example. What i am saying is that when you change the Hours of a day in the Project settings, and have custom work days, the...
Forum: OmniPlan General 2010-02-16, 03:36 PM
Replies: 16
Views: 10,443
Posted By stephenrussett
Ok but that does not explain by the Gantt does...

Ok but that does not explain by the Gantt does not update. The gantt shows the duration. So shouldnt the Gantt and the Duration column be equal to each other? Meaning that if i change the project...
Forum: OmniPlan General 2010-02-16, 02:38 PM
Replies: 16
Views: 10,443
Posted By stephenrussett
Right i understand why the duration was changing....

Right i understand why the duration was changing. My confusion is why the gantt chart was not updating to represent the change.

Can you explain your second paragraph again. It is very confusing....
Forum: OmniPlan General 2010-02-16, 01:55 PM
Replies: 16
Views: 10,443
Posted By stephenrussett
Anyone try this?

Anyone try this?
Forum: OmniPlan Extras 2010-02-15, 10:09 PM
Replies: 6
Views: 15,879
Posted By stephenrussett
What are the import solutions for basecamp? ...

What are the import solutions for basecamp?

Why not just make yourself a HTML report with the columns/format for basecamp and then print into the HTML report
Forum: OmniPlan General 2010-02-15, 10:04 PM
Replies: 7
Views: 10,658
Posted By stephenrussett
mmmmm we really need a way to see the critical...

mmmmm we really need a way to see the critical path even with locked in dates. :(
Forum: OmniPlan General 2010-02-15, 08:44 PM
Replies: 7
Views: 10,658
Posted By stephenrussett
Also what would be the gap of time that OP...

Also what would be the gap of time that OP considers wiggle room?

would 1 day be wiggle room? Is there any way to change this?

Thanks
Forum: OmniPlan General 2010-02-15, 08:41 PM
Replies: 7
Views: 10,658
Posted By stephenrussett
Ok most likely in this case then i have a few...

Ok most likely in this case then i have a few activities which are locked in dates. These dates cannot occur as early as possible. They have to be exact dates. Will the critical path not continue...
Forum: OmniPlan General 2010-02-15, 08:07 PM
Replies: 7
Views: 10,658
Posted By stephenrussett
Critical Path Question

I am having some issues with the Critical Path. When i run critical path, the very last 2 activities and final mile stone get marked as critical path, but nothing else connected through dependencies...
Forum: OmniPlan General 2010-02-15, 04:48 PM
Replies: 2
Views: 5,132
Posted By stephenrussett
Auto Lead Time

Is there a way to set a default lead time? for all tasks? Or maybe a script that would add a default lead time to all tasks or selected tasks?
Forum: OmniPlan General 2010-02-15, 04:47 PM
Replies: 3
Views: 4,155
Posted By stephenrussett
:) was kinda hoping that it was already a feature...

:) was kinda hoping that it was already a feature :)
Forum: OmniPlan General 2010-02-15, 03:55 PM
Replies: 1
Views: 6,631
Posted By stephenrussett
Bug: Priority Column WBS Auto-highlight

When you are on activity 1 in the effort column and press the down arrow key to activity 2 the effort is automatically selected/highlighted.

When you are in the Priority Column and do the same...
Forum: OmniPlan General 2010-02-15, 03:52 PM
Replies: 3
Views: 4,155
Posted By stephenrussett
FR: Colour Coding Days

Would be great if we could be able to mark days with colours. So say Friday Feb 26 was a very important day (for whatever reason). I could mark that day/column in red. Or even mark entire activity...
Forum: OmniPlan General 2010-02-15, 03:49 PM
Replies: 1
Views: 4,525
Posted By stephenrussett
Merge Inspector into Main Window

Is there a way to merge the inspector into the main window?

I know you can just resize the window to account for the inspector, but i find it nice sometimes to have the inspector window locked...
Forum: OmniPlan General 2010-02-15, 12:32 PM
Replies: 0
Views: 3,796
Posted By stephenrussett
Summary Header level Gridline Colours

We need a way to change the summary level gridlines in the Gantt. So for example i am working with a gantt atm with summary level that shows: [First day of week] - [last day of week] [Month] ...
Forum: OmniPlan General 2010-02-15, 12:27 PM
Replies: 1
Views: 6,142
Posted By stephenrussett
mmmm found the alternating line colour that...

mmmm found the alternating line colour that works. But some gridline options would be nice too
Forum: OmniPlan General 2010-02-15, 12:24 PM
Replies: 16
Views: 10,443
Posted By stephenrussett
Possible Bug, can someone please confirm - Effort-Duration-Change of days per day

Ok here is the situation.

Create an activity with a effort of 8h.
Assign it to someone with a work schedule of:Mon 9am - 3pm, and Thur 9am - 12pm.

Make sure your project hours per day is set...
Forum: OmniPlan General 2010-02-15, 12:15 PM
Replies: 1
Views: 6,142
Posted By stephenrussett
Printing Outline with Gridlines??!!

Is there not a way to print the WBS outline (without Gantt) with gridlines. Even better quesiton is there a way to add gridlines to the WBS within omniplan?

I know you can use the HTML report to...