Search: Posts Made By: zbacon
Forum: OmniPlan General 2010-08-19, 06:32 AM
Replies: 7
Views: 12,600
Posted By zbacon
I was afraid of that - thanks for the...

I was afraid of that - thanks for the confirmation, at least! Wanted to make sure I wasn't missing an easier way...
Forum: OmniPlan General 2010-08-11, 09:11 AM
Replies: 7
Views: 12,600
Posted By zbacon
Ok, I keep running into this, so I need some...

Ok, I keep running into this, so I need some advice - I've confirmed I can't do it the way I'd like (up to X% of this resource), but how do you other OmniPlan users handle the following situation?
...
Forum: OmniPlan General 2010-07-28, 05:35 AM
Replies: 7
Views: 12,600
Posted By zbacon
Yes! I did mean OmniPlan. (I'm an iPad junkie, so...

Yes! I did mean OmniPlan. (I'm an iPad junkie, so I have Omnifocus for iPad on the brain with the imminent release!) ;)

That's too bad about the resource assignment - I can't imagine it's an...
Forum: OmniPlan General 2010-07-27, 10:15 AM
Replies: 7
Views: 12,600
Posted By zbacon
How to Assign Resources "up to" X %??

Example: Four concurrent tasks, one resource

Task 1: 10 hours (effort)
Task 2: 10 hours
Task 3: 10 hours
Task 4: 50 hours

25% of 100% of the resource assigned to each task

Good thing:...