I have work (drywalling) which mostly takes place in sequence, but 5% of that work has to wait until another major task group is complete. I can leave both task groups intact, and just create dependencies between the relevant subgroups (between the two major task groupings), which means my dependency lines in the Gantt chart will make some pretty long vertical lines, but the task groupings remain intact, which I think I prefer. Or I could break the major task groups up, which would make the tasks more linear, but breaking up the major groups seems unappealing. Curious how others approach this.

Bob