I am trying to use OmniPlan as a basic planning (not tracking) tool and it is really making things difficult.

I have a project outlined with numerous tasks, their efforts and durations, appropriate resources assigned, etc. I have also set the start dates to be LOCKED for those things that I know are in the past (ie. already underway).

Give this setup, I add a new task that needs to be completed. I assign resources and ask Omniplan to re-level things. I expect it to move the new task into a spot where it fits with resource allocations, etc. I do NOT expect anything else to happen, since nothing else has changed.

Instead, Omniplan moves the start date for nearly all of my in-progress tasks up by a few days. This, despite the fact that their start dates are locked.

The behavior seems to have something to do with the completion percentages assigned to the various tasks.

Why, oh why, is Omniplan moving things whose start date is locked? If it thinks they are behind schedule it should give me a warning of some sort. It should NOT blithely move them around on me.

Is there something I don't understand here?