Thread: Remaining Costs
View Single Post
Is there any way in OmniPlan to show remaining costs? That is, if I have a task that is 100k, and it is 75% complete, is there any way to show that there is 25k of cost remaining on the tasks. Ideally this would work just like the cost, and roll up the task hierarchy calculating totals.