I'm also seeing efforts displayed as fractions of days. My tasks start on day one at 8 am and end on day X at 5 (which is what my work calendar considers an entire day: 8-5). However, I end up with efforts that are fractional. I've been able to edit some manually, others seem linked to other fractional tasks and changing one just cascades into the next.

All tasks are set to begin as early as constraints allow. Which, strangely, seems to reset at times to begin on a set date. Different thread.

I can provide more detail. But help would be appreciated.