I've got a fairly simple project plan, 5 resources, covering 90 days. However, there are over 585 discrete WBS tasks. My problem is that the Gantt display is ugly since the display is littered with "resource tags" showing who is assigned to that task. I want to be able to view the Gantt chart as just that...a gantt chart.

Is there a way to turn off these tags? I've searched the forums for "gantt tags" or "bar tags" and can't come up with anything.

Thanks.