Hi Rachael,

That's good to know, and thank you for the screen shot. I have another (more important) question based on your attached picture. On each day, you currently have Resource 1 working on only one task at a time. (And similarly with Resource 2.) Now, can you set each Resource's time to be split equally between Project 1 and Project 2 and then have these projects proceed in parallel? (Of course, each project would then take longer to do.) These are the sorts of things we often need to do, and that's what I mean by sharing resources across projects. I would like the levelling to be able to handle this automatically. Can you do this? If so, I would be very grateful if you could provide instructions on how to get the leveller to do this and also attach another screen shot. Thanks.