I would like to see a "maximum hours devoted to task each day" feature.

Creating multiple "virtual resources" to handle this situation (what I understand Ken to be saying) would turn into a nightmare in my project. I've got 15 tasks in the project, with three staff resources handling those jobs over a period of months. Splitting those three staff into multiple staff resources as a workaround would throw off the entire timeline. Especially since some tasks require a staff resource's full time.