Originally Posted by stephenrussett View Post
Ok most likely in this case then i have a few activities which are locked in dates. These dates cannot occur as early as possible. They have to be exact dates. Will the critical path not continue through the locked in date?
The critical path will not continue thru a locked date because with the date being locked, nothing before the locked task can delay the locked task's start date. (Similar behavior to having a task set with a "on specified date" schedule).

Quote:
Originally Posted by stephenrussett View Post
Also what would be the gap of time that OP considers wiggle room?
1 second is considered wiggle room. In other words, there's zero slack time for critical path currently. We have a feature request to allow the slack time to be a user-definable setting which I'll add a vote for you.